The record across the network:
Killardry Bridge

Killardry Bridge, 2014 to 2026: a €450 parapet repair the Council said in February 2026 was still not carried out

Killardry Bridge · the inspection record · source-led

The bridge record, in the Council's own documents

4 March 2014 — Principal inspection (Eirspan, TS-LP3101-001.00). Component 4, Parapets/Safety barrier: "Some loose/missing stones and some repointing is required on both parapets." Costed works: masonry repointing, year 2017, €250; masonry repair, year 2017, €200. Minimum parapet height 0.55 m. Approach skew 90°. — the document record

20 June 2024 — Maintenance inspection. Overall "Warning". Parapets rated "Good". No comments, no work follows. — what the Council knew

21 January 2025 — Engineering inspection (TY-L3151-B-010). Overall "Significant Damage". Capping of the downstream wall "partly removed"; four areas of missing stonework upstream, two downstream. The same report records "Is Signage Present? No." — what the Council knew

7 February 2025. The national rural local-road default speed limit changed from 80 to 60 km/h.

24 April 2025. Bronagh English, 18, died at the bridge — 93 calendar days after the "Significant Damage" rating. The documents held record no repair and no signage in that interval; they are not proof that no later measure was ever taken.

18 February 2026 — the Council's FOI internal-review decision. "Accordingly, the repair works listed in the report have not been carried out to date." "Typically, funding is allocated to fund works on 5 to 10 bridges each year." — the internal-review decision

The procedure the Council's own manual sets out

The Bridge Asset Management System guidelines describe the response to an immediate public-safety risk: the MD Engineer to check the structure in person and determine whether immediate temporary measures "to make the road safe, such as signing and guarding, are required." The public record does not show who received the January inspection or what assessment followed. Whether any local response was required or made remains an evidence question — the 93-day record.

The same district, the same year

In January 2026, at the Tipperary–Cahir–Cashel Municipal District, Councillor Declan Burgess put on record that "Over €400,000 now has been given to the greenway project from Cahir to Cashel, and we still haven't got a design, we still haven't got a route selected, and there's been no further consultations." The District Engineer undertook to bring a report to the members. Active Travel funding; a separate stream from bridge funding — the greenway record.

What this page establishes, and what it does not

The family's position: Bronagh's family believes that the measure the Council's own manual describes — signing and guarding at a damaged, unsigned parapet — would have been enough. As they said on record, "One small cone and she'd be with us" (Tipperary Live, October 2025). The repair the Council's 2014 inspection costed at €450 was, on the Council's own February 2026 account, still not carried out; in the same district a greenway had reached €400,000 of spend with no route. Those are separate funding streams and the family does not say one should have paid for the other; it asks how the district's attention was set. That is presented as the family's position, not as a finding about any person's knowledge, motive, responsibility or causation.

Sources

Factual record. No finding of causation or responsibility is made here.

Road Death Tipp

Tipperary road deaths — remembrance and records

Remembrance and the official records, county by year.

Open the map

Partial map coverage. No ages shown.

Partial map coverage. No ages shown.